Tuesday, September 19th 2023

TSMC to Invest Additional $4.5 Billion at Arizona Fab

TSMC has gained the Taiwanese government's approval to invest $4.5 billion in its main North American manufacturing hub—Fab 21 is located in the greater Phoenix area. Mass production at the Arizona foundry has been delayed into 2025 due to behind-schedule equipment installations and various workforce-related issues, but a limited trial run is reported to begin early next year. Mid-last month, the TSMC executive board sought approval from Taiwan's Investment Commission for an additional overseas spend (the Arizona operation is registered as a subsidiary company).

This request was approved by the commission yesterday (September 18)—a $3.5 billion cash injection was already given the thumbs-up back in March. Exact areas of expenditure have not been declared to the public, but Taiwanese media outlets believe that the second phase of funds will be marked for working capital expenses at the North American division. Short-term business costs include the purchase of inventory (e.g raw materials), day-to-day operating expenses and resolvement of short-term debts. Mark Liu, TSMC's chairman, recently expressed optimism about goings-on at Arizona's Fab 21—mentioning significant progress made over the spring and summer period.
Sources: UDN Taiwan, Wccftech, Fronteras (image source)
Add your own comment

6 Comments on TSMC to Invest Additional $4.5 Billion at Arizona Fab

#1
Space Lynx
Astronaut
the semi-truck bringing in water budget will be double this once the drought continues. :roll:
Posted on Reply
#2
trsttte
Space Lynxthe semi-truck bringing in water budget will be double this once the drought continues. :roll:
They should really budget for a pipeline to the ocean and a desalination plant, would be a big positive for Arizona as well since the government seems unable to move on that
Posted on Reply
#3
bonehead123
If they were to go the west by southwestern route, it's only about 170 miles, which would be about the same or even a tad shorter than some LNG pipelines, and we all know how cheap those are to build.. :eek:..:fear:..:cry:

For comparisons sake, the last pipeline project I was involved in several years ago was ~130 miles long (give or take) and the costs for the pipe & fittings alone was in excess of $700M....which was mostly 36", some 24" and the rest 18" corrosion-proof, cathodically-protected 316-grade Stainless Steel, but did NOT included the valves, pumps, compressors, metering & regulator stations or other ancillary parts or costs...

Just sayin, hey TSMC, this is your bankers calling, and we are NOT in a good mood, hehehe !
Posted on Reply
#4
BlaezaLite
$4.5 billion? Cheapskates. 10 years that'll be a KFC and bottle of Pepsi.
Posted on Reply
#5
trsttte
bonehead123For comparisons sake, the last pipeline project I was involved in several years ago was ~130 miles long (give or take) and the costs for the pipe & fittings alone was in excess of $700M....which was mostly 36", some 24" and the rest 18" corrosion-proof, cathodically-protected 316-grade Stainless Steel, but did NOT included the valves, pumps, compressors, metering & regulator stations or other ancillary parts or costs...
Underwater/ground or above ground pipeline? Either way, TSMC is pumping about 44.5 Billion (counting with this extra 4.5) into the Arizona Fab, another billion into a water pipeline that the government of Arizona would easily give some subsidies to (because they also desperately need something like that) doesn't seem like all that much

I mean, it even pays for itself in some years compared to moving water by truck
Posted on Reply
#6
bonehead123
trsttteUnderwater/ground or above ground pipeline? Either way, TSMC is pumping about 44.5 Billion (counting with this extra 4.5) into the Arizona Fab, another billion into a water pipeline that the government of Arizona would easily give some subsidies to (because they also desperately need something like that) doesn't seem like all that much

I mean, it even pays for itself in some years compared to moving water by truck
It was mostly underground for LNG...also, note that the $700M from my post above does NOT include land/right of way purchases/leases, legal fees, construction/installation labor costs :D

But I agree, a few billion here, a few billion there....TSMC will quickly get that money back, and moar, once the fab is online, and the state will get a substantial increase in tax collections from all the new employees buying stuff, building houses etc :)
Posted on Reply
Dec 21st, 2024 21:51 EST change timezone

New Forum Posts

Popular Reviews

Controversial News Posts