Intel Ohio Fab Equipment Deliveries Delayed by Extreme Weather

Intel is aiming to get its $20 billion fabrication location—in New Albany, Ohio—up and running by 2025, but the advanced manufacturing facility is facing another round of setbacks. According to a WCMH NBC4 local news report (covering the Colombus, Ohio area), a planned "oversized equipment" reshuffle has been delayed—the shifting of heavy machinery was supposed to start last weekend. Extreme weather conditions (flooding) have been cited as major factor, as well as the complicated nature of transporting "overweight and oversized" loads to Team Blue's 1000-acre site. Workers are set to resume efforts this weekend—starting no later than February 17. Tom's Hardware has kept tabs on the Ohio fab's progress: "The project to move the equipment is expected to last over nine months, meaning this phase of Intel's construction could be done near the end of 2024. There isn't a firm indication of how much work remains to be done at the site after the equipment is delivered." TPU previously covered the leading-edge location's indefinitely postponed groundbreaking ceremony—CHIPS Act subsidies were not delivered in an expected timely manner back in 2022.

A couple of media outlets (Tom's Hardware, Network World, etc.) have received an official statement regarding the slippage of events in New Albany: "While we will not meet the aggressive 2025 production goal that we anticipated when we first announced the selection of Ohio in January, 2022, construction has been underway since breaking ground in late 2022 and our construction has been proceeding on schedule. Typical construction timelines for semiconductor manufacturing facilities are 3-5 years from groundbreaking, depending on a range of factors...We remain fully committed to the project and are continuing to make progress on the construction of the factory and supporting facilities this year. As we said in our January 2022 site-selection announcement, the scope and pace of Intel's expansion in Ohio may depend on various conditions." Industry insiders believe that an "opening ceremony" could occur around late 2026, or even early 2027.
Sources: NBC4i, Tom's Hardware, Network World
Add your own comment

8 Comments on Intel Ohio Fab Equipment Deliveries Delayed by Extreme Weather

#1
AnarchoPrimitiv
Good. Anything that results in Intel losing marketshare in the x86 space is objectively good for consumers.
Posted on Reply
#2
Wirko
Will electric power delivery to the fab be similarly fragile?
Posted on Reply
#3
FoulOnWhite
AnarchoPrimitivGood. Anything that results in Intel losing marketshare in the x86 space is objectively good for consumers.
Bet you would not say that if it was AMD having the problem. Talk about bias
Posted on Reply
#4
bonehead123
T0@stCHIPS Act subsidies were not delivered in an expected timely manner back in 2022.
HAHAHAHA.........Bureaucracy 101 at it's finest :D

So what they are essentially sayin is that they can't/won't do anything to keep things moving on schedule until/unless the gov't coughs up their (taxpayer's) share of the $$ to help them pay for it.....heaven forbid they should have to spend some of their own money.....meanwhile, their execs continue buying up yachts, beachhouses etc, and stuffing uber-mega bonuses into their bank accounts...
Posted on Reply
#5
kondamin
bonehead123HAHAHAHA.........Bureaucracy 101 at it's finest :D

So what they are essentially sayin is that they can't/won't do anything to keep things moving on schedule until/unless the gov't coughs up their (taxpayer's) share of the $$ to help them pay for it.....heaven forbid they should have to spend some of their own money.....meanwhile, their execs continue buying up yachts, beachhouses etc, and stuffing uber-mega bonuses into their bank accounts...
You make it sound as if they are members of congress or in the defence industry
Posted on Reply
#6
bonehead123
kondaminYou make it sound as if they are members of congress or in the defence industry
They're all in the same corrupt, conglomerated clusterf*ck in one way or another IMO :D
Posted on Reply
#7
Tropick
Flooding? what the hell are they talking about? We've only had a few days of rain here in Jan/Feb there's no flooding whatsoever. This is absolute bullshit
Posted on Reply
#8
JoeTheDestroyer
TropickFlooding? what the hell are they talking about? We've only had a few days of rain here in Jan/Feb there's no flooding whatsoever. This is absolute bullshit
I had the same thought. I assume they mean flooding somewhere else on the route to here, rather than around Columbus itself.
Posted on Reply
Nov 17th, 2024 09:18 EST change timezone

New Forum Posts

Popular Reviews

Controversial News Posts